Electrical Substation: Pad Construction and Civil Foundation
Arguijo Corp. was selected to execute the first phase of civil construction for a new electrical substation in the Permian Basin. Construction phasing was altered after award due to time restraints on transformer deliver showcasing Arguijo's agility. Scope included: all dirt work required to build the 275'x280' pad, facility fencing, placing approx. 245CY of concrete for 3-ea transformer foundations including pedestals, containment floor/walls/sump systems, and fabricating/installing all grating systems for each containment. All work completed safely and on schedule.