20" Meter Station Construction
Arguijo was tasked with the construction of a new 20" meter station/interconnect tying one of our existing clients into a new customer in the TX Panhandle. Arguijo crews completed all fabrication, mechanical, and civil scopes required for the project. Facility included the installation of: 1-20"x24" hot tap, 1-20" inlet filter separator, 1-ultrasonic meter skid, 1-flow control valve skid, 1-10" control valve setting with bypass, and 1-100BBL condensate tank. Due to commercial obligations, all work was completed under a compressed schedule requiring enhanced work hours and coordination with subcontractors. All work completed safely and on schedule.