South of Midland, TX Wellsite Gas Processing Facility
I. Scope of Work Furnished equipment and operations for Wellsite Facility including: • (1) Cat 3516 Inlet Gas Compressor • (2) Skid Mounted 65 ton Mechanical Refrigeration Units (MRU) with NGL Stabilizer Towers • (4) 18,000 gallon NGL Bullet Tanks with unloading bulkheads •Full Operations & Maintenance II. Contract Type Rental contract including equipment and operations III. Overview - Due to the pre-packaged, single skid design, Torrent was able to install and commission equipment on the existing facility. - Processed ~6.0 MMscfd of 1450 Btu gas. Removed the majority of C3+ as well as dehydrated the gas stream to less than 5#/MMscfd using our skid mounted TRU-65 MRUs. - The equipment operated reliably and met all required gas conditioning and NGL specifications. - Used the conditioned gas to provide the fuel to the inlet gas compressor & generators. IV. Equipment included: • ASME Code Equipment • PLC Controlled Automated Process • Design Basis for Broad Operating Ranges • Robust Equipment for Improved Run-time